Question: PROBLEM 3: NETWORK DIAGRAM&GANTT CHART I. Create a network diagram using the data presented in Table 1 and identify the critical path. 2. Convert your
PROBLEM 3: NETWORK DIAGRAM&GANTT CHART I. Create a network diagram using the data presented in Table 1 and identify the critical path. 2. Convert your network diagram into a Gantt chart. DurationDependencies Task TI T2 (days) 12 T4 TS T6 T7 T8 T9 TI T2 T3 T4, T6 17 TS, T8 Table 1: Activity table Task Duration in Weck 123 4 5 67 89 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 10