Question: What is one method to establish a team's velocity? a. Compare The average Story points completed throughout the previous Iterations b. Add the Story points
| What is one method to establish a team\\\'s velocity? |
| a. Compare The average Story points completed throughout the previous Iterations |
| b. Add the Story points for all Features completed in the Iteration |
| c. Add the Story points for all the Stories planned for the iteration |
| d. Calculate the percentage planned versus actual stories completed during an Iteration. |