Question: A project consisting of the following activities: Activity Predecessor Duration (months) A 2 B Activity A Duration (hours) 1 Predecessor 3 C 2 B

A project consisting of the following activities: Activity Predecessor Duration (months) A 

A project consisting of the following activities: Activity Predecessor Duration (months) A 2 B Activity A Duration (hours) 1 Predecessor 3 C 2 B 5 1 DE F B A, B 4 3 C 3 1 FB D 3 2 B 2 G F, C 5 HC Identify the critical path and obtain the project completion time. Calculate free float for each activity. The table describes the activities needed in planning a training session. E 1 4 H G 4 I JK F I, D J 3 2 1 F 4 4 G 1 5 Determine the critical path and the expected completion time of the training session. H 3 3,6 L E 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer To determine the critical path and the expected completion time of the training session we need to perform a critical path analysis This analysis involves calculating the earliest start time ES ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!