Question: 0 2 pts swered Question 4 7 A simple CPM network has three activities, D , E , and F . D is an immediate
pts
swered
Question
A simple CPM network has three activities, D E and F D is an immediate predecessor of E and of F E is an immediate predecessor of The activity durations are
The critical path is DEF duration
Both The critical path is DEF duration and Slack at D is periods are true.
Slack at is periods.
Slack at is periods.
The critical path is DF duration
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
