Question: 0 2 pts swered Question 4 7 A simple CPM network has three activities, D , E , and F . D is an immediate

02 pts
swered
Question 47
A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4,E=3,F=6.
The critical path is D-E-F, duration 12.
Both The critical path is D-E-F, duration 12 and Slack at D is 0 periods are true.
Slack at E is 3 periods.
Slack at D is 0 periods.
The critical path is D-F, duration 10.