Question: Question 2 ( 1 point ) A simple CPM network has three activities, D , E , and F . D is an immediate predecessor

Question 2(1 point)
A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F.E is an immediate predecessor of F. The activity durations are D=5,E=4,F=9.
The critical path is D-F, duration 14.
The critical path is D-E-F, duration 18.
Slack at E is 4 units.
The network has two critical paths.
Slack at D is 4 units.