Question: Question 2 ( 1 point ) A simple CPM network has three activities, D , E , and F . D is an immediate predecessor
Question point
A simple CPM network has three activities, D E and F D is an immediate predecessor of and of is an immediate predecessor of The activity durations are
The critical path is DF duration
The critical path is DEF duration
Slack at is units.
The network has two critical paths.
Slack at D is units.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
