Question: [ 0 3 ] ( 1 5 + 1 0 Mark ) A . The process in figure [ 1 ] contains dryer that is

[03](15+10 Mark)
A. The process in figure [1] contains dryer that is used to dry a particular solid from 26% to 6% moisture (dry basis). If the constant time required is 120min, the data on the drying curve is shown in table below. Investigate what would be the weight of dry material in feed, then calculate the total design time for this process.
\table[[Kg water ?Kg dry solid,0.3,0.2,0.18,0.15,0.14,0.11,0.07,0.05],[Drying rate kghr.m2,1.22,1.22,1.14,0.90,0.80,0.56,0.22,0.05]]
 [03](15+10 Mark) A. The process in figure [1] contains dryer that