Question: 0 . 5 points eBookPrintReferencesCheck my workCheck My Work button is now enabledItem 2 A manager wants to assign tasks to workstations to achieve an
points
eBookPrintReferencesCheck my workCheck My Work button is now enabledItem
A manager wants to assign tasks to workstations to achieve an hourly output rate of units. Assume that the shop works minutes per hour ie no breaks
picture
a Assign the tasks shown in the above precedence network times are on the nodes and are in minutes to workstations using the following heuristic rules: iAssign the task with the most followers.ii Tiebreaker: Assign the task with the longest time.Round the intermediate calculations and final answers to decimal places.
Workstations Task Idle Time
a
b c
d e f
g h
b What is the efficiency? Round the intermediate calculations to decimal places. Round the final answer to decimal place.
Efficiency
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock