Question: 04 Slack duration is equal to- Select one: a. EF-ES b. LS-ES c. LF-ES d. LF-BF e. LS-EF 07 Which of the following statements is

04

Slack duration is equal to-

Select one:

a. EF-ES

b. LS-ES

c. LF-ES

d. LF-BF

e. LS-EF

07

Which of the following statements is true for a CPM network?

Select one:

a. A network can have multiple critical paths.

b. Only Start and End activities have a slack.

c. The duration of the critical path is the average duration of all paths in the project network.

d. Every activity of a network has a slack.

e. The shortest path of the network is called critical path.

09

Which of the following statements is true for every activity of a CPM network?

Select one:

a. ES less than or equal to LS

b. LS is less than ES.

c. ES = LF - Duration

d. LS= ES - duration

e. LS = ES + duration

22

Which of the following statements is true for a CPM network?

Select one:

a. The slack of all the activities is non-zero.

b. The slack of all the activities is positive.

c. The slack of all the activities is zero.

d. The slack of activities on the critical path is negative.

e. The slack of all the activities on the critical path is zero.

23

The sequence of stages in which a product is processed is captured by-

Select one:

a. Check sheet.

b. Pareto chart.

c. Flowchart.

d. Poka-yoke.

e. Taguchi map.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!