Question: 0.5 / 0.5 pts Question 19 To complete the first setup on a new machine took an employee 300 minutes. Using an 85% cumulative average-time
0.5 / 0.5 pts Question 19 To complete the first setup on a new machine took an employee 300 minutes. Using an 85% cumulative average-time learning curve indicates that the second setup on the new machine is expected to take 277.50 minutes 255 minutes 210 minutes 127.50 minutes