Question: QUESTION 21 To complete the first setup on a new machine took an employee 100 minutes. Using an 80% cumulative average-time learning curve indicates that

QUESTION 21 To complete the first setup on a new machine took an employee 100 minutes. Using an 80% cumulative average-time learning curve indicates that the second setup on the machine is expected to take: A. 30 minutes B. 40 minutes C. 60 minutes D. 80 minutes QUESTION 21 To complete the first setup on a new machine took an employee 100 minutes. Using an 80% cumulative average-time learning curve indicates that the second setup on the machine is expected to take: A. 30 minutes B. 40 minutes C. 60 minutes D. 80 minutes