Question: 1 0 . 2 Examine the network schedule with its activities, their durations, and initial cost plus extra cost for acceleration in the table. Draw

10.2 Examine the network schedule with its activities, their durations, and initial
cost plus extra cost for acceleration in the table. Draw its network diagram,
determine the critical path, perform a timecost trade-off analysis to minimize the
total project duration and accelerated cost, and record your
steps.
Name Initial Accelerated
Activity Successor Time Cost Time Extra
A B, E 2 wk $2 Same None
B C 3 wk $31 wk $5
C D, G 3 wk $32 wk $6
D H 2 wk $21 wk $2
E F 2 wk $2 Same None
F G 2 wk $21 wk $3
G H 3 wk $32 wk $2
H 2 wk $21 wk $3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!