Question: 1 0 3 b ) What is the expected completion time of the critical path? What is the expected completion time of the other path
b What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?
c What is the variance of the critical path? What is the variance of the other path in the network?
d If the time to complete path is normally distributed, what is the probability that this path will be finished in weeks or less?
e If the time to complete path is normally distributed, what is the probability that this path will be finished in weeks or less?
f Explain why the probability that the critical path will be finished in weeks or less is not necessarily the probability that the project will be finished in weeks or less. PX
W Rich Cole Control Devices, Inc., produces custombuilt relay devices for auto makers. The most recent project undertaken by Cole requires different activities. Cole's managers would like to determine the total project completion time in days and those activities that lie along the critical path. The appropriate data are shown in the following table.
a What is the probability of being done in days?
b What date results in a probability of completion?
d What is the provaus or less? day
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning
tabletablethe
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock