Question: 1 0 minutes per unit. Part 2 is simultaneously processed at workstation C for 2 0 minutes per unit. Work stations B and C feed

10 minutes per unit. Part 2 is simultaneously processed at workstation C for 20 minutes per unit. Work stations B and C feed the
parts to an assembler at workstation D, where the two parts are
assembled. The time at workstation D is 15 minutes.
a) What is the bottleneck of this process?
b) What is the hourly capacity of the process?