Question: 1 0 * * * * Question: * * What does the critical path in project management represent? A ) The longest duration path through

10**** Question:** What does the critical path in project management represent?
A) The longest duration path through the project network
B) The shortest duration path through the project network
C) The project initiation phase
D) The project closing phase
 10**** Question:** What does the critical path in project management represent?