Question: # 1 0 Using the data below, calculate the squared error for the 4 th week. Use the 2 period moving average to create the

#10
Using the data below, calculate the squared error for the 4 th week. Use the 2 period moving average to create the forecast.
\table[[Week,Time Series Value],[1,8.00],[2,6.00],[3,14.00]]
Answer format: Number: Round to: 1 decimal places.