Question: 1 1 : 0 1 LTE 5 1 it 4 1 3 - Apr - 2 0 2 4 1 0 - 3 3 -

11:01
LTE
51
it413-Apr-202410-33-53(2)
SECTION A
Answer all questions in this section
(20 marks)
What is the main advantage of using the NPV method as a basis for project selection?
a. It takes into account the time value of money.
b. It is easy to calculate and understand.
c. It considers only the cash inflows of the project.
d. None of the above.
What document formally authorizes a project and defines its scope?
a. Project Schedule
b. Work Breakdown Structure
c. Project Scope Statement
d. Gantt Chart
How can a well-structured communication plan contribute to project success?
a. By reducing project scope
b. By eliminating project risks
c. By fostering collaboration and preventing misunderstandings
d. By accelerating project timelines
How does the Net Present Value (NPV) method account for the time value of money?
a. It ignores the time value of money.
b. It discounts future cash flows to present value.
c. It inflates past cash flows to present value.
d. It uses the average cash flow over time.
Which stage in the project life cycle is typically the longest and most resourceintensive?
a. Initiation
b. Planning
c. Execution & monitoring
d. Closing
What is the critical path in a project schedule?
a. The shortest path to project completion
b. The longest path to project completion
c. The path with the most tasks
d. The path with the least dependencies
In a WBS, which level represents the highest level of abstraction?
a. Level 1
b. Level 2
c. Level 3
d. Level 4
Which of the following is a potential limitation of the weighted decision model?
a. It is subjective and may be biased by individual preferences.
b. It is time-consuming and may be difficult to implement.
2
c. If may nol take into account all relevant fictors.
(1. All of the nhove,
What doev the term "filoat" or "Slack" represent in project scheduling?
a. Free time available for a tusk without delaying the project
b. The weight of a task in the projeet
c. The flexibility of project managers
d. Time added to a task to ensure completion
c. Increasing the resources allocated to activities on the critical path.
d. Identifying and mitigating risks that could impact the critical path.
How does a detailed project charter contribute to project success?
a. By providing a basis for detailed project execution
b. By minimizing stakeholder engagement
c. By preventing project risks
 11:01 LTE 51 it413-Apr-202410-33-53(2) SECTION A Answer all questions in this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!