Question: 1 1 - 2 5 The air pollution project discussed in the chapter has progressed over the past several weeks, and it is now the

11-25 The air pollution project discussed in the chapter
has progressed over the past several weeks, and
it is now the end of week 8. Leslie Harky would
like to know the value of the work completed, the
amount of any cost overruns or underruns for the
project, and the extent to which the project is ahead
of or behind schedule by developing a table like
Table 11.8. The revised cost figures are shown in
the following table: