Question: 1 1 . All activities must be project. A . successor, started B . successor, completed C . predecessor, started D . predecessor, completed before

11. All
activities must be
project.
A. successor, started
B. successor, completed
C. predecessor, started
D. predecessor, completed
before a new activity can be started in a