Question: 1 1 . Given the table of setup and queue times as below, if the required part quantity Q = 1 0 0 and the
Given the table of setup and queue times as below, if the required part quantity Q and the cost rate is $hrs Please answer the following questions. points
a If the shop floor is a job shop, whats the manufacturing lead time? Whats the total cost?
b If the shop floor is a batch shop, what is the manufacturing lead time? Whats the total cost?
Op No
Setup & Queue hrs
Processing min