Question: 1 1 point table [ [ activity predecessors normal _ time,crash _ time,normal _ cost crash _ cost ] , [ A , ,
point
tableactivity predecessors normaltime,crashtime,normalcost crashcostABACBDCEBFE
The table shows normal time, crash time, normal cost, crash cost of activities in a project. According to this table which activity must be crashed first? Only enter the name of the activity. Lower or uppercase both work. Ex: A or a Copyrighted content. Cannot be posted. @orsdemir
type your answer...