Question: 1 1 point table [ [ activity predecessors normal _ time,crash _ time,normal _ cost crash _ cost ] , [ A , ,

1
1 point
\table[[activity predecessors normal_time,crash_time,normal_cost crash_cost],[A,,3,1,4500,12500],[B,A,6,2,3000,13000],[C,B,2,1,2500,6000],[D,C,3,1,3000,5000],[E,B,6,4,4500,7500],[F,E,5,4,5000,8000]]
The table shows normal time, crash time, normal cost, crash cost of activities in a project. According to this table which activity must be crashed first? (Only enter the name of the activity. Lower or uppercase both work. Ex: A or a. Copyrighted content. Cannot be posted. @orsdemir)
type your answer...
 1 1 point \table[[activity predecessors normal_time,crash_time,normal_cost crash_cost],[A,,3,1,4500,12500],[B,A,6,2,3000,13000],[C,B,2,1,2500,6000],[D,C,3,1,3000,5000],[E,B,6,4,4500,7500],[F,E,5,4,5000,8000]] The table shows normal

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!