11. Your critical path is 128 days long. The next longest path is 122 days long.
a. If you extend the longest path by 5 days, the entire project duration will increase by 5 days. True or false?
b. If you reduce the longest path by 5 days, the entire project duration will decrease by 5 days. True or false?
c. If you reduce the longest path by 10 days, the entire project duration will decrease by 10 days. True or false?