Question: 1 2 4 points 7 . Given the network shown above, what is the latest finish time for activity B ? 5 1 0 1

12
4 points
7. Given the network shown above, what is the latest finish time for activity B?
5
10
13
11
8
 12 4 points 7. Given the network shown above, what is