Question: Given the network shown above, what is the earliest start time for activity F? 9 10 12 15 18 Given the network shown above, what

- Given the network shown above, what is the earliest start time for activity F?
- 9
- 10
- 12
- 15
- 18
- Given the network shown above, what is the latest finish time for activity C?
- 12
- 6
- 4
- 9
- 15
- Given the network shown above, what is the slack time for activity B?
A. 0
B. 3
C. 5
D. 7
E. 9
- Given the network shown above, what is the slack time for activity D?
A. 0
B. 3
C. 6
D. 8
E. 10
Use the following to answer the next four questions: B(4) D(3) A(2) F(4) C(7) E(6)