Question: 1 2 . Consider the following MRP record: Problems 2 1 7 Week 1 Gross requirements 2 3 4 5 6 2 5 3 0

12. Consider the following MRP record: Problems 217 Week 1 Gross requirements 234562530515510 Scheduled receipts 5015 Projected available balance 35103025102010 Planned order releases Q =lot-for-lot; LT =5; SS =0. Suppose 15 units of the scheduled receipt for 50 units due on Monday of week 2 are scrapped during week 1, and no scrap ticket is issued. Furthermore, assume this lot isnt counted before its put away in the stockroom on Monday of week 2, but is recorded as a receipt of 50 units. What impact will these actions have on factory operations?