Question: 1 2 PLEASE ANSWER IN CHART FORMAT TO MATCH QUESTION manufacturing lead time of two weeks. The mounting hardware is purchased from a sheet steel
PLEASE ANSWER IN CHART FORMAT TO MATCH QUESTION
manufacturing lead time of two weeks. The mounting hardware is purchased from a sheet steel company and has a threeweek lesd time. The finish trim is purchased from a Taiwan electronics company with offices in Los Angeles as prepackaged units consisting of knobs and various trim pieces. Trim packages have a twoweek lead time. Final assembly time may be disregarded because adding the trim package and mounting are performed by the customer.
Audio Products supplies wholesalers and retailers, who place specific orders for both models up to eight weeks in advance. These
points
orders, together with enough odditional units to satisfy the small number of individual sales, are summarized in the following demand schedule:
tableMadeWEEKStandard model,,,,Sports model,,,,,
There are currently radioCD units on hand but no trim packages or mounting hardware.
Prepare a material requirements plan to meet the demand schedule exactly. Specify the gross and net requirements, onhand amounts, and the planned order relesse and receipt periods for the radioCD chassis, the standard trim and sports car model trim, and the standard mounting hordwore and the sports cor mounting hardwore.
Note: Leave the cells blank, whenever zero is required.
tablePerlod:,Standard Model Demand:,,,,Sports Madel Dermand:,,,,,tableRadiaCDOH: LT: SS: Q: LLGross requirements,,,,,,,,Scheduled receipts,,,,,,,,Projected avalable balance,,,,,,,,Net requirements,,,,,,,,Planned ander receipts,,,,,,,,Planned arder releases,,,,,,,,tableStandard TrimOH: LT: SS: Q: LLGross requirements,,,,,,,,Scheduled receipts,,,,,,,,Projected avalable balance,,,,,,,,Net requirements,,,,,,,,Planned arder receipts,,,,,,,,Planned arder releases,,,,,,,,tableStandard HWOH: LT: SS: Q: LLGross requirements,,,,,,,,Scheduled receipts,,,,,,,,Projected avaliable balance,,,,,,,,Net requirements,,,,,,,,Planned arder receipts,,,,,,,,Planned arder releases,,,,,,,,tableSport TrimOH: LT: SS: Q: LLGross requirements,,,,,,,,tableScheduled receiptsPrajected avalable balance,,,,,,,,Net requirements,,,,,,,,Planned ander receipts,,,,,,,,Planned ander releases,,,,,,,,tableSport HWOH: LT: SS: Q: LLGross requirements,,,,,,,,Scheduled receipts,,,,,,,,Projected avalable balance,,,,,,,,Net requirements,,,,,,,,Planned ander receipts,,,,,,,,Planned arder releases,,,,,,,,Audio Products supplies wholesalers and retailers, who place specific orders for both models up to eight weeks in advance. These orders, together with enough additional units to satisfy the small number of individual sales, are summarized in the following demand schedule:
Model WEEK
Standard model
Sports model
There are currently radioCD units on hand but no trim packages or mounting hardware.
Prepare a material requirements plan to meet the demand schedule exactly. Specify the gross and net requirements, onhand amounts, and the planned order release and receipt periods for the radioCD chassis, the standard trim and sports car model trim, and the standard mounting hardware and the sports car mounting hardware.
PLEASE ANSWER IN CHART FORMAT
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock