Question: 1 2 . When extending a project network, one problem is that under the standard finish - to - start relationship, you cannot start the

12. When extending a project network, one problem is that under the standard finish-to-start relationship, you cannot start the next activity until the predecessor activity is complete. You can overcome this problem by breaking activities further into segments and starting a new activity once the appropriate segment is complete. This technique is called:
A. An AON Network
B. Concurrent engineering
C. Lagging
D. Laddering
E. Staggering
F. Crashing