Question: 1 2 . When extending a project network, one problem is that under the standard finish - to - start relationship, you cannot start the
When extending a project network, one problem is that under the standard finishtostart relationship, you cannot start the next activity until the predecessor activity is complete. You can overcome this problem by breaking activities further into segments and starting a new activity once the appropriate segment is complete. This technique is called:
A An AON Network
B Concurrent engineering
C Lagging
D Laddering
E Staggering
F Crashing