Question: An information on a project contains in a table below, each activity is labeled with A to K along with other information time in week.

An information on a project contains in a table below, each activity is labeled with A to K along with other information time in week.

1) Complete information in the tables columns for the project Expected Time & Variance. (5 markah/marks)

An information on a project contains in a table

2) Determine the time of the project can be completed and critical path. (2 markah/marks)

3) Complete the table and slack for the project. (2 markah/mark)

An information on a project contains in a table

4) Construct a figure of AON node configuration network based on answer 1. (9 markah/marks)

5) What is the probability that the project will be completed two weeks before its expected completion date with an illustration? (4 markah/marks)

6) Complete the spaces in Normal Time and Crash Cost Per Week. (4 markah/marks)

An information on a project contains in a table

7) Calculate the total new project cost and the crashing cost if the completion time can be reduced by six weeks based on information in the table at question six (6).

(4 markah/marks)

Activity Predecessor Optimistic Pessimistic Expected Variance Time (O) Most Likely 6 2 1 4 8 2 3 3 1 6 5 4 6 8 9 3 12 11 17 4 5 1 6 2 7 1,2 2 1,3 2 4,6 2 6,8 5 7, 10 1 7 1 8 4 4 4 9 1 2 3 2 5 10 11 7 16 8 9 Early Start Early Finish Late Start Late Finish Slack Activity 1 2 3 4 5 6 7 8 9 10 11 Activity Predecessor Normal Time (t) Normal Cost ($) 1000 2000 Crash Time (t) 4 Crash Cost Per Week 1 2 1 3 1,2 500 5 Crash Cost (S) 1400 2500 800 2200 1250 4600 2000 3800 2 1300 5 4 5 1,3 850 5 2 6 2 4000 7 4, 6 1 2 8 1500 3000 1200 2 9 1600 1 10 900 3 6, 8 5 7, 10 Total 1800 3800 11 800 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!