A firm spent $6,500 last week to repair some of its equipment. This week the company is trying to decide whether the equipment could be better utilize by assigning it to a proposed project. When analyzing the proposed project, the $6,500 should be treated as which type of cost?
Multiple Choice
Opportunity
Fixed
Incremental
Erosion
Sunk