Question: 1 3 . 2 6 ( Optional - Based on Earned Schedule discussion in Appendix 1 3 . 1 . Suppose you have a project
OptionalBased on Earned Schedule discussion in Appendix Suppose you have a project with a Budget at Completion BAC of $ and a projected length of months. After tracking the project for six months, you have collected the information in the table below.
a Complete the table. How do Earned Value SPI based on $ and Earned Schedule SPI differ?
b Calculate the schedule variances for the project for both Earned Value and Earned Schedule. How do the values differ?
tableJan,Feb,Mar,Apr,May,JunPV $EV $SV $SPI $ES mo
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
