Question: 1 3 . 3 8 Suppose your PV for a project was $ 1 0 0 , 0 0 0 and your EV was $
Suppose your PV for a project was $ and your EV was $ Your Schedule Performance Index SPI for this project would be:
a
b
c You cannot calculate SPI with the information provided