Question: Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are
Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is thiscost?
.png)
Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 50 60 70 100 90 100 0 60 Initial project duration 15 Total direct cost $
Step by Step Solution
3.46 Rating (159 Votes )
There are 3 Steps involved in it
ACT NORMAL TIME A 5 B 3 4 M A B C D E F G H 5 3 2 5 2 5 2x 3 4x D 2 E 5 NORMAL MAXIMUM ... View full answer