Question: 1 3 4 5 7 Job Processing Time Due Date 2 9 21 6 5 8 3 6 5 4 3 4 2 22 12

1 3 4 5 7 Job Processing Time Due Date 2 9 21 6 5 8 3 6 5 4 3 4 2 22 12 13 12 34 36 Processing time and due date of 8 jobs are given above. i) ii) Find a sequence to minimize total tardiness of 8 jobs. Find a sequence to minimize the number of tardy jobs (jobs with tardiness > 0). . You are free to generate sequences by any method you like (i.e. any algorithm or just an intuition). Try to find a result less than 50 for the first question, and less than 5 for the second question (if you cannot find, just do your best) Submit an excel formulas for each calculation ation