2. Ten jobs are processed through a single machine. The processing times and due dates are given below. 8 4 20 9 7 25 10 6 30 Job 1 2 3 4 5 6 7 Processing time 3 4 2 1 6 5 8 Due date 5 7 9 20 | 10 | 12 11 Determine the sequence of the jobs in order to minimize a) mean flow time b) number of tardy jobs c) maximum lateness d) what is the make span for any sequence