Question: 1 3. BD has developed the tasks, durations, and predecessor relationships in the following table for part of a new business system. Task Immediate Predecessor(s)

1 3. BD has developed the tasks, durations, and predecessor relationships in the following table for part of a new business system.

Task

Immediate Predecessor(s)

Time to Complete

A

None

8

B

A

6

C

A

4

D

B

3

E

B

6

F

C

4

G

D

4

H

E, F

3

Draw the network diagram for the project. What are the ES/EF (earliest start/finish) and the LS/LF (latest start/finish) for each task? Hint: It may be helpful to create dummy start and/or end tasks with task times of 0 to tie the ends of the network together.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!