Question: a) The expected (estimated) time for activity C is _____ weeks. (Round your response to two decimal places.) b) The variance for activity C is

a) The expected (estimated) time for activity C is _____ weeks. (Round your response to two decimal places.)
b) The variance for activity C is ___weeks. (Round your response to two decimal places.)
c) Based on the calculation of the estimated times, the critical path is _______
d) The estimated time for the critical path is ____ weeks. (Round your response to two decimal places.)
e) The activity variance along the critical path is _____weeks. (Round your response to two decimal places.)
Homework: Homework 6: Project Management Save Score: 0 of 1 pt 9 of 10 (10 complete) HW Score: 59.29%, 5.93 of 10 pts X Problem 3.17b Question Help Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Activity m Time (weeks) a m b 6 8 10 1 9 24 9 14 18 4 7 10 1 3 4 5 9 21 B D Immediate Predecessor(s) CE F Immediate Predecessor(s) Activity G A H A A J B K 2 2 7 6 1 3 2 7 8 1 b 4 2 7 14 4 DGH CE a) The expected (estimated) time for activity Cis weeks. (Round your response to two decimal places.) 1))) Enter your answer in the answer box and then click Check Ans 5 Pemaining Clear All CheckStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts