Question: 1 . 3 Exercise 3 An excavation work between retaining walls for an underground passage project was carried out in a soil with an initial

1.3 Exercise 3
An excavation work between retaining walls for an underground passage project was carried out
in a soil with an initial 4-meter-thick gravel stratum, followed by an intermediate 10-meter thick
sand stratum, and finally, a 15-meter thick stratum of very dense clay. The phreatic level was 2,5
meters below ground surface.
The excavation height is 8 meters and was implemented in 2-meter-high load steps. In the case
of the retaining walls, they are made of 1-meter-thick and 12-meter-high reinforced concrete. For
the construction of these retaining walls, three perpendicular tubular steel struts were installed,
with a 70cm diameter and 60mm thickness, with vertical and horizontal spacings of 2 meters;
the first strut was installed one meter from the wall head. At the end of the excavation works, a
70- cm-thick reinforced concrete floor slab was laid at the bottom and a 60- cm-thick concrete
slab was set at the head of the retaining wall to cover the underground passage. Next, the steel
struts were pulled out.
Currently, a 5-floor residential building project is intended to be carried out 15 meters from the
existing retaining walls, whereas each floor represents a 30kPa load on the soil with a length of
30 meters length.
As a geotechnical engineer, you have been tasked with conducting an analysis on the possible
impact the construction works will have on the passage's retaining walls and slabs. In order to
conduct tis analysis, you must create a Plaxis 2D numerical model, and consider the following
questions:
What elements would you use to model the problem's components (retaining walls, steel
struts, slabs, loads, etc.)?
What construction phases should the model use?
What mechanical calculation types should be performed to analyze the problem correctly?
What essential results should be rigorously analyzed?
1 . 3 Exercise 3 An excavation work between

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!