Question: 1 3 . For an activity the optimistic time is 2 minutes, most likely time is 3 minutes and the pessimistic time is 8 minutes.

13. For an activity the optimistic time is 2 minutes, most likely time is 3 minutes and the pessimistic time is 8 minutes. What is the variance of the activity
A.0
B.0.25
C.0.5
D.1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!