Question: Q 2 . An advertising project manager is planning a new advertising campaign. In addition, the manager gathered the time information for each activity. The
Q An advertising project manager is planning a new advertising campaign. In addition, the manager gathered the time information for each activity. The precedence relationships of the activities are shown in the Table below.
begintabularlcccccc
hline Table : Time Estimate weeks
hline Activity & begintabularc
Optimistic
time
endtabular & begintabularc
Most Likely
time
endtabular & begintabularc
Pessimistic
time
endtabular & begintabularc
Immediate
Predecessor
endtabular & begintabularc
Expected
time Te
endtabular & Variance
hline A & & & & Start & &
hline B & & & & Start &
hline D & & & & B &
hline E & & & & A &
hline F & & & & A C &
hline G & & & & B &
hline
endtabular
A Calculate the expected time Te and variance for each activity
B Draw the network
C Determine the critical path, using the expected times Te as activity duration.
D How long will the advertising campaign project take?
E Calculate the slack for each activity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
