Question: 1 3 . Using _ _ _ _ _ _ _ _ _ level cost estimates, a projected duration and cost estimate of the entire

13. Using _________ level cost estimates, a projected duration and cost estimate of the entire project can be provided to project stakeholders when later project stage details are not known.
a. Analogous.
b. Parametric.
c. Bottom-up.
d. Summary.