Question: 1 4 - 4 . For the project outlined in the following table, prepare ( a ) a bar chart, ( b ) an AOA

14-4. For the project outlined in the following table, prepare (a) a bar chart, (b) an AOA network
diagram, and (c) AON network diagram. (d) What and how long is the critical path?
Task Follows Task(s) Weeks Duration Manning Level
A Start 6.03
B Start 5.04
C Start 5.03
D A 3.02
E A, B 6.05
F D, E, C 1.02
14-5. For the project in Problem 14-4,(a) provide a worker-level profile, assuming that all tasks begin
as early as possible; (b) repeat the profile, assuming that no more than nine people are available in
any week and the manning level for a task cannot change; and (c) identify the project duration in
each case.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!