Question: 1 4 - 8 Companies usually estimate work based on how many units of work a staff person can do in a month, usually called
Companies usually estimate work based on how many units of work a staff person can do in a month, usually called manmonths or sometimes development months, staff months, person months, or for example, engineer months. If the work must be estimated in manweeks, the manhours per month are actually available for actual direct labor work.
our company has received a reques for. oys earin in of your customers, and man comeny a decided to submit a bid. Only one agerrestim in your company win bed mirag to pet hand the work and the department manager estimates that hours p direct labor will be required.
You or will be regu calculate the number of hours he filable in a typical manmonth.
The Hum first opies Department provides you with the following yearly history forthe average employee in the company:
Vacation weeks
: Pat daidays
Paid holidays days
Jury duty day
a How many direct labor hours are available per month per person?
b If only one employee can be assigned to the project, what will be the duration of the effort, in months?
c If the customer wants the job completed within one year, how many employees should be
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock