Question: 1 4 - 8 Companies usually estimate work based upon man - months. If the work must be estimated in man - weeks, the man
Companies usually estimate work based upon manmonths. If the work must be estimated in manweeks, the manmonth is then converted to manweeks. The problem is in the determination of how many manhours per month are actually available for actual direct labor work.
COST CONTROL
Your company has received a request for proposal RFP from one of your customers and management has decided to submit a bid. Only one department in your company will be required to perform the work and the department manager estimates that hours of direct labor will be required.
Your first step is to calculate the number of hours available in a typical manmonth. The Human Resources Department provides you with the following yearly history for the average employee in the company:
Vacation weeks
Sick days days
Paid holidays days
Jury duty day
A How many direct labor hours are available per month per person?
B If only one employee can be assigned to the project, what will be the duration of the effort, in months?
C If the customer wants the job completed within one year, how many employees
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock