Question: 1 5 . 2 . A process costs $ 2 0 0 to set up . The run time is 5 minutes per piece and

15.2. A process costs $200 to set up. The run time is 5 minutes per piece and run cost is $36 per hour. Determine the following:
A. The fixed cost
B. The variable cost
C. The total cost and unit cost for a lot of 600
D. The total cost and unit cost for a lot of 1200