Question: 1 7 . 1 0 . Today is day 4 of the planning cycle. Sequence the following jobs by FCFS , SPT , SLACK, and

17.10. Today is day 4 of the planning cycle. Sequence the following
jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow
time and mean tardiness for each sequencing rule. Which rule would
you recommend?
Job
Processing Time
(in days) Due Date
A 310
B 1012
C 225
D 48
E 515
F 818
G 720