Question: 1 8 . Cost performance required to be achieved on the remaining work is expressed by CV SPI CPI TCPI 1 9 . What is

18. Cost performance required to be achieved on the remaining work is expressed by
CV
SPI
CPI
TCPI
19. What is the best way to accurately calculate Estimate to Completion (ETC)
(BAC - EV)/ CPI
Manual forecasting of cost of the remaining work
BAC - EV
EAC - AC
20. Two efficiency indicators that reflect cost and schedule performance of a project areAdd
description here!
Cost Performance Index (CPI) and Schedule Performance Index (SPI)
Earned Value (EV) and Actual Cost (AC)
Cost Projection Index (CPI) and Schedule Projection Index (SPI)
Actual Cost (AC) and Planned Value (PV)
21. A project is estimated to cost $200,000 with a timeline of 10 months. Due to shipment
delay, the schedule was slightly delayed. This was however made up by receiving the first
batch of materials for the project by air. The net result was that there was some additional
cost in the project. At the end of the second month, he project manager reviews the project
and finds that the project is 20% complete and actual costs are $50,000. The Estimate to
Complete (ETC) for the project would be
$60,000
$150,000
$40,000
$160,000
22. Schedule Variance (SV) greater than zero implies that
Project is ahead of schedule
EV is less than PV
Project progress is as per the baseline plan
Project is behind schedule
23. A project is scheduled to complete in one year. After 3 months of execution the earned
value is $45,000 and the planned value is $55,000. What is the schedule variance of the
project?
$55,000
$45,000
$10,000
-$10,000
24. CPI less than one implies that
Project performance is as per baseline plan
Actual Cost (AC) is less than Planned Value (PV)
Project is over budget
Project is under budget
25. Earned Value (EV) minus Actual Cost (AC) is
Cost Variance (CV)
Cost Performance Index (CPI)
Schedule Performance Index (SPI)
Schedule Variance (SV)
26. What is the best way to calculate the Estimate At Completion (EAC) when original
estimates are no longer valid.
EAC = AC +[(BAC EV)/(CPI x SPI)]
EAC = AC + BAC EV
EAC = BAC/CPI
EAC = AC + Bottom-up ETC
27. What is EAC for the project if BAC = $50,000 AC = $10,000 EV = $7,000 manual bottom up
ETC = $50,000
$73,000
$60,000
$67,000
$50,000
28. A project is estimated to cost $50,000 with a timeline of 50 days. After 25 days, the
project manager finds that 80% of the project is complete and Actual costs are $50,000. What
is the Cost Performance Index (CPI)?Add description here!
CPI is 2
CPI is 1
CPI is 0.8
CPI is 1.5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!