Question: 1 8 . Cost performance required to be achieved on the remaining work is expressed by CV SPI CPI TCPI 1 9 . What is
Cost performance required to be achieved on the remaining work is expressed by
CV
SPI
CPI
TCPI
What is the best way to accurately calculate Estimate to Completion ETC
BAC EV CPI
Manual forecasting of cost of the remaining work
BAC EV
EAC AC
Two efficiency indicators that reflect cost and schedule performance of a project areAdd
description here!
Cost Performance Index CPI and Schedule Performance Index SPI
Earned Value EV and Actual Cost AC
Cost Projection Index CPI and Schedule Projection Index SPI
Actual Cost AC and Planned Value PV
A project is estimated to cost $ with a timeline of months. Due to shipment
delay, the schedule was slightly delayed. This was however made up by receiving the first
batch of materials for the project by air. The net result was that there was some additional
cost in the project. At the end of the second month, he project manager reviews the project
and finds that the project is complete and actual costs are $ The Estimate to
Complete ETC for the project would be
$
$
$
$
Schedule Variance SV greater than zero implies that
Project is ahead of schedule
EV is less than PV
Project progress is as per the baseline plan
Project is behind schedule
A project is scheduled to complete in one year. After months of execution the earned
value is $ and the planned value is $ What is the schedule variance of the
project?
$
$
$
$
CPI less than one implies that
Project performance is as per baseline plan
Actual Cost AC is less than Planned Value PV
Project is over budget
Project is under budget
Earned Value EV minus Actual Cost AC is
Cost Variance CV
Cost Performance Index CPI
Schedule Performance Index SPI
Schedule Variance SV
What is the best way to calculate the Estimate At Completion EAC when original
estimates are no longer valid.
EAC AC BAC EVCPI x SPI
EAC AC BAC EV
EAC BACCPI
EAC AC Bottomup ETC
What is EAC for the project if BAC $ AC $ EV $ manual bottom up
ETC $
$
$
$
$
A project is estimated to cost $ with a timeline of days. After days, the
project manager finds that of the project is complete and Actual costs are $ What
is the Cost Performance Index CPIAdd description here!
CPI is
CPI is
CPI is
CPI is
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
