Question: 1 8 . On the bill for a Time & Materials contract, you see the following line items. LABOR Labor Category Labor Rate Hours Used

18. On the bill for a Time & Materials contract, you see the following line items. LABOR Labor Category Labor Rate Hours Used Designer $200/hour 100 Architect $300/hour 200 Engineer $250/hour 400 MATERIALS Item Cost Fee Building Materials $300,0005% Tools $200,000-- Vehicle Rental $50,0002% How much does your project owe?