Question: On the bill for a Time & Materials contract, you see the following line items. LABOR Labor Category Labor Rate Hours Used Designer $200/hour 100
- On the bill for a Time & Materials contract, you see the following line items.
| LABOR | ||
| Labor Category | Labor Rate | Hours Used |
| Designer | $200/hour | 100 |
| Architect | $300/hour | 200 |
| Engineer | $250/hour | 400 |
| MATERIALS | ||
| Item | Cost | Fee |
| Building Materials | $300,000 | 5% |
| Tools | $200,000 | -- |
| Vehicle Rental | $50,000 | 2% |
How much does your project owe? (5 points)