Question: 1 9 5 points A project that has several near - critical or critical paths is said to be inherently risky. fully consumed. elastic. insensitive.

19
5 points
A project that has several near-critical or critical paths is said to be
inherently risky.
fully consumed.
elastic.
insensitive.
sensitive,