Question: 1 9 ] A project manager is analyzing the cost variance of a construction project. The budgeted cost of work scheduled ( BCWS ) is

19] A project manager is analyzing the cost variance of a construction project. The budgeted cost of work scheduled (BCWS) is $500,000, the actual cost of work performed (ACWP) is $450,000, and the budgeted cost of work performed (BCWP) is $480,000. Calculate the Cost Variance (CV), Schedule Variance (SV), Cost Performance Index (CPI), and Schedule Performance Index (SPI). Provide a detailed explanation and set up the calculations in Excel. [ SOLVE THE QUESTION USING EXCEL ]