Question: 1. A five-year Project X has projected net cash flow of so, $ 200 000, S 800 000, $ 800 000 and $ 500 000

1. A five-year Project X has projected net cash flow of so, $ 200 000, S 800 000, $ 800 000 and $ 500 000 in the next five years. It will cost $ 1900 000 to implement the project. If the inflation rate is 5% stable throughout the year, calculate the NPV. IS it a good project? Why? (2.5 marks) 2. From the information given draw the following What is the total completion time? Gantt chart (2.5 marks) ii) network diagram (2.5 marks) iii) What if activity E delays and becomes 6 weeks. Give the new completion time. (2.5 marks) Fredecessor Time (weck Amy A E 12 1. 1
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock